Project Summary

Introduction

The Poulton Library refurbishment project was commissioned to upgrade the existing library facilities, improving accessibility, energy efficiency, and functionality for the local community. The works were undertaken on behalf of a local authority client, aiming to modernise the space while preserving its vital role as a community learning and engagement hub.

Project Overview

Modernising a Community Hub While Maintaining Public Access

The project was delivered over a 12 week period, with phased works carefully programmed to minimise disruption to ongoing library operations and surrounding public areas. The refurbishment focused on enhancing building performance, safety, and usability while maintaining continuous access for the local community wherever possible.

Project Details

Property Type

Public Library

Client

Lancashire County Council

Scope

Refurbishment and Upgrade Works

Occupancy

Property remained closed throughout works

Challenges

Overcoming Challenges

Solutions

How We Delivered

Window & Glazing Upgrades

Full window replacement with high-performance UPVC glazing to improve insulation and reduce energy consumption.

Internal Layout & Meeting Space

Installation of new partition walls using the Truline System 3000 FD30, creating a meeting room with integrated blinds, fire rated glass, and power/data points.

Fire Safety Enhancements

New FD30 fire doors with full height vision panels, alongside upgraded smoke alarms and system improvements to meet current safety standards.

External Envelope & Cladding

Comprehensive cladding replacement including vapour barriers, insulation, and vertical composite boards for durability and weather resistance.

Internal Finishes

Decorative wall finishes and optional ceiling treatments to improve aesthetics and user experience.

Final Completion & Handover

Full sparkle clean ensuring the facility was ready for immediate use upon completion.

Value Added

  • Improved comfort, safety, and usability of the library
  • Delivered long term durability through low maintenance materials
  • Enhanced building performance and energy efficiency
  • Provided modern, flexible spaces for community use

Public Impact

  • Created a more accessible and welcoming environment for local residents
  • Enabled improved community engagement through new meeting spaces
  • Supported continued library operations throughout the refurbishment
  • Reinforced the library’s role as a key community asset

Social Value

This project demonstrates a strong commitment to sustainable construction and community focused delivery. By improving energy efficiency, reducing the building’s carbon footprint, and enhancing public facilities, the scheme supports the local authority’s environmental goals while investing in long term community wellbeing.

Project Cost

£150,000.0

16 Weeks

Duration

£150,000

Total Cost

Poulton

Location

Unoccupied

During Works

Before Gallery

During Gallery

After Gallery