Our Work
Boat House Youth
Project Summary
- Start date: 21st January 2026
- Completion date: 22nd January 2026
Introduction
Bambers Building Contractors were appointed by Boathouse Youth to install a specialist moveable acoustic wall within the main hall of their community facility, following the successful completion of a wider improvement project delivered the previous year. Previous Case Study
The objective was to transform a single large hall into two flexible, functional spaces that could support simultaneous activities while maintaining acoustic separation.
Community buildings increasingly need to support a wide range of activities for young people and local residents. Creating flexible, sound controlled environments enables multiple uses within the same space, improving accessibility, comfort and overall building efficiency.
Project Overview
Creating flexible, multi use community space without structural alteration
The scope of works involved the installation of a specialist moveable acoustic partition wall to divide the main hall into two separate, usable areas.
The new sliding wall system allows the client to create a meeting space alongside ongoing activities, host multiple youth sessions at the same time, maximise building use without structural alterations and adapt the layout depending on operational requirements.
The acoustic specification ensures that activities can take place independently in each area without disruption, significantly enhancing the building’s overall functionality.
Project Details
Property Type
Community Youth Facility
Client
Boathouse Youth
Scope
Installation of a specialist moveable acoustic partition wall to divide a large hall into two functional spaces
Occupancy
Live community facility (occupied throughout works)
Challenges
Overcoming Challenges
- Delivering works within a live community facility
- Requirement to complete installation outside of business hours
- Avoiding disruption to staff, youth sessions and community users
- Achieving precise acoustic performance standards
- Ensuring safe and smooth operation of the system
Solutions
How We Delivered
- Close coordination with Boathouse Youth to programme works out of hours
- Collaboration with specialist subcontractor gointeriors.co.uk
- Careful planning and sequencing of installation
- Strict adherence to health and safety requirements
- Precision installation to meet acoustic and operational standards
Acoustic Performance Upgrade
Installation of a high performance soundproof moveable wall system, enabling activities to run simultaneously without noise disruption.
Flexible Space Configuration
The hall can now be easily reconfigured to suit different activities, providing adaptable space for changing needs.
Multi Use Functionality
Creation of two independent areas allows meetings, youth sessions and activities to run concurrently.
Increased Building Usability
Modernisation of the internal layout improves how the facility is used day to day.
Specialist Installation
Delivered in partnership with gointeriors.co.uk, ensuring high quality installation and system performance.
Future Proofed Design
The system allows the space to expand or contract as required, supporting long-term community use and flexibility.
Value Added
For the Community
- Increased access to activities through more flexible use of space
- Improved comfort through reduced noise disruption
- Greater inclusivity through the provision of quiet, focused environments
- Enhanced wellbeing through improved spatial design
For the Client
- Improved asset utilisation without major structural alterations
- Long term flexibility within the building
- Increased operational efficiency
- Enhanced functionality and future adaptability
PUBLIC IMPACT
The newly installed sliding wall will play an integral role in how the facility operates moving forward. It enables the hall to be used for active sessions while simultaneously providing a quieter office or meeting space, significantly improving the building’s usability.
By increasing flexibility within the facility, the project supports broader community engagement, improved youth provision and more effective service delivery.
This is a strong example of how relatively small scale, well specified upgrades can deliver meaningful social impact within community buildings.
PROJECT COST
Total Cost: £9,000.00
2 Days
Duration
£9,000
Total Cost
Blackpool
Location
Closed
During Works